data centers / microsoft-project-osmium
operational

Microsoft Project Osmium

5855 SW Kerry St, Cumming, IA 50061 · United States

Microsoft Project Osmium is an operational AI data center with AI chips owned by Microsoft and used by OpenAI. It currently hosts an estimated 156k H100-equivalents of compute, supported by 190 MW of IT power at a capital cost of $7.2B. It is estimated to use A100,H100,B200 chips.

Current IT power190 MW
Current compute156k H100-eq
Current cost$7.2B

Buildout

IT Power Compute Cost
— estimated (satellite, permits, disclosures)--- projected by Epoch AI

Hardware

Site & affiliations