Microsoft Fairwater Wisconsin

4800 90th St, Mount Pleasant, WI 53403 · United States

Microsoft Fairwater Wisconsin is an operational AI data center with AI chips owned by Microsoft and used by OpenAI, Microsoft. It currently hosts an estimated 446k H100-equivalents of compute, supported by 369 MW of IT power at a capital cost of $14.0B. By 2028-05, Epoch AI projects it to reach 4.53M H100-eq, 2.26 GW of IT power and a cost of $85.7B. It is estimated to use B200 chips.

Current IT power369 MW
Current compute446k H100-eq
Current cost$14.0B
Projected IT power2.26 GWby 2028-05
Projected compute4.53M H100-eqby 2028-05
Projected cost$85.7Bby 2028-05

Buildout

IT Power Compute Cost
— estimated (satellite, permits, disclosures)--- projected by Epoch AI