Microsoft Fairwater Atlanta
1435 Hwy 54 W, Fayetteville, GA 30214 · United States
Microsoft Fairwater Atlanta is an operational AI data center with AI chips owned by Microsoft and used by OpenAI, Microsoft. It currently hosts an estimated 769k H100-equivalents of compute, supported by 636 MW of IT power at a capital cost of $24.1B. It is estimated to use B200 chips.
Current IT power636 MW
Current compute769k H100-eq
Current cost$24.1B